Detailed installation instructions are supplied with each consignment. Also available on request.

1. To set the recommended gutter height ensure the gutter front is 10mm below the pitch of roof.

2. Fix fascia brackets with 32mm x Nr10 Roundhead stainless steel screws Code SC201. Drill pilot holes for each fixing screw.

3. Fix fascia brackets at 915mm centres, either nominally level, or to a falls of 1:600

4. Support outlets and angles by fixing fascia brackets a maximum of 150mm from each side.

5. Apply two 8mm dia beads of sealant central to the gutter socket. Do not carry out jointing in wet conditions, or temperatures below 4 deg C and above 40 deg C

6. Finger tighten nut and bolt only, pull the joint apart sideways to ensure a minimum 3mm expansion gap is achieved. Then tighten one full turn only. Point sealant into joint gap adding sealant if required. Clean off any excess with Solvent cleaner SC108.
NB: Jointing should not be carried out in wet weather, temperatures below 5°C or above 40°C