- To set recommended gutter height, fix a straight batten on the lowest profile of the roof covering. The gutter can then be offered up to the intersection point (10mm below the pitch of roof, as shown).
- Fix fascia brackets with 32mm x No10 roundhead screws, SC201.
- Fix fascia brackets at 1 metre centres, nominally level or to falls of 1:600.
- Fix all gutter angles using 2 no 32mm x No10 countersunk screws, SC202.
- Position outlets and fix using 32mm x No10 countersunk screws, SC202.
- Ensure all joint surfaces are clean and dry. Use a clean cloth with solvent cleaner, SC108.
- Ensure the factory fitted rubber compression spacers are attached to the inside of the union. Apply two 8mm thick parallel beads of sealant, SC101 to each side of the union. Do not carry out jointing in wet weather of temperatures below 5°C or above 40°C.
- Fit union to end of gutter as shown.
- Fit gutter into fascia brackets by first inserting the rear up stand, then snapping down the front. Repeat sequence 6, 7 & 8 to the next length of gutter and joint the gutter lengths together.
- Anchor each union by slightly pulling the gutter union apart and inserting a 32mm x No 10 countersunk screw, SC202 into the fascia via the hole provided. Ensure a 3-5mm expansion gap is left.
- Point sealant into expansion gap between gutter ends and ensure the anchor screw is covered.
- Point sealant into edges and clean off surplus with solvent cleaner, SC108.
NB: Jointing should not be carried out in wet weather, temperatures below 5°C or above 40°C